This paper Principles of Engineering · all yearsQ. 1 · An electronics company is considering…Q. 2 · A project with the detail…Q. 3 · Write a short note on…Q. 4 · Classify the software testing techniques…Q. 5 · In the context of independent…Q. 6 · What is a flexible manufacturing…Q. 7 · An organisation has done some…With this paperPart-I MCQs1← 20222023 →
3 hours · questions hide until you reveal them

Not yet checked 3 of 7 questions have not yet been compared with the official paper.

Q. 1

An electronics company is considering the options of either (a) immediately proceeding with production of an innovative product which has just completed prototype testing or (b) having a value analysis team complete a study. If the company proceeds with option (a), the firm expects with a probability of 0.6, that sales would be 100,000 units at 550 e a c h , a l s o t h e r e e x i s t s a p r o b a b i l i t y o f 0.4 t h a t s a l e s m a y r e m a i n a t 75 , 000 u n i t s a t 550 each, also there exists a probability of 0.4 that sales may remain at 75,000 units at 550 e a c h , a l so t h er ee x i s t s a p r o babi l i t y o f 0.4 t ha t s a l es ma y r e maina t 75 , 000 u ni t s a t 550 each. If the company pursues option (b), the firm expects with a probability of 0.7, that sales would be 75,000 units at 750 e a c h w h e r e a s t h e r e e x i s t s a p r o b a b i l i t y o f 0.3 f o r t h e s a l e s t o r e m a i n a t 70 , 000 u n i t s a t 750 each whereas there exists a probability of 0.3 for the sales to remain at 70,000 units at 750 e a c h w h er e a s t h er ee x i s t s a p r o babi l i t y o f 0.3 f or t h es a l es t or e maina t 70 , 000 u ni t s a t 750 each. Value analysis, at a cost of $100,000 is only used in option (b) whereas no further cost factor needs consideration for option (a) as it is ready to be launched. Use decision tree analysis to recommend which option should be taken by the company.

Not yet checked
(20)
Q. 2
  1. (a)A project with the detail of its activities as shown below, was started on 20/1/2022. If the project has a delay of 02 weeks after 06 working weeks, what would be its new delivery date? Activity A B C D E F G H I K Duration (weeks) 3 4 4 2 3 3 4 4 5 6 Following Activity B,D,E C I F G H I K [10]
  2. (b)What is Project Integration Management? Write Processes of Project Integration Management. [10]
Not yet checked
(20)
Q. 3
  1. (a)Write a short note on the benefits of international quality management system (e.g ISO) certification. [10]
  2. (b)What do you understand by "cost of quality"? Write a note on various categories of quality costs. [10]
(20)
Q. 4
  1. (a)Classify the software testing techniques commonly used in practice. Explain the testing spectrum specifying the person who will do any specific testing along with general scope. [10]
  2. (b)Describe and then differentiate the static and structural White Box testing techniques in detail. [10]
(20)
Q. 5
  1. (a)In the context of independent demand models, what is the difference between "fixed-period (P) system” and “fixed-quantity (Q) system”? [5]
  2. (b)A hotel distributes a mean of 1000 bath towels per day to guests in their rooms. The demand is normally distributed with a standard deviation of 100 towels per day, based on the occupancy. The laundry firm that has the contract as supplier of these towels to the hotel, requires a 2-day lead time. The hotel targets 98% service level to satisfy customer (guest) expectations. What should be the safety stock? What is the re-order point (ROP)? To what extent (in %), the hotel would need to vary its safety stocks than those calculated in part (a) if the policy changes to the risking stock outs at 10%? Table for areas under the Normal Curve is provided [15]
(20)
Q. 6
  1. (a)What is a flexible manufacturing system (FMS)? Write a short note on the various benefits associated with a FMS system if implemented successfully in an Organization. [10]
  2. (b)What is "Agile Manufacturing"? Provide an overview of the concept and some possible approaches as to how this may be achieved by Organizations. [10]
(20)
Q. 7

An organisation has done some estimation of the complexity of four of its current projects and has ranked them out of 10 against the headings shown in the following table: Organisational Complexity Resource Complexity Technical Complexity Project 1 1 7 6 Project 2 4 4 5 Project 3 4 2 1 Project 4 2 9 4 In the absence of any further information, if the organisation wanted to apply the Prince 2 methodology to only one of the projects, which one would you recommend?

Not yet checked
(20)

Related papers

About this paper

The 2022 PMS Punjab Principles of Engineering paper set by the PPSC. Question wording only; questions marked “Not yet checked” have not been compared with the official paper yet.

Disclaimer Prep Right is independent and not affiliated with PPSC.